A 2,400 m² prefabricated office delivered as a complete kit, with local installation supervised by our technicians.2,400 平方米预制办公楼,成套供货,由我方技术人员指导当地安装。
| Location项目地点 | Guatemala City, Guatemala危地马拉 危地马拉城 |
|---|---|
| Building type建筑类型 | Two-storey office building两层办公楼 |
| Dimensions建筑尺寸 | 60 × 20 m, 2 floors, 3.6 m floor height60 × 20 米,2 层,层高 3.6 米 |
| Floor area建筑面积 | 2,400 m²2,400 平方米 |
| Steel weight用钢量 | About 180 t incl. decking约 180 吨(含压型钢板) |
| Facade外立面 | Insulated panels + glazed entrance保温板 + 玻璃入口 |
| Delivery交付周期 | Nine weeks to site九周运抵现场 |
A trading company needed new head offices on a site with restricted access and a short rainy-season window for construction. Concrete would have taken too long.一家贸易公司需要新建总部,场地进出受限,且雨季前施工窗口很短,混凝土方案工期无法满足。
Steel columns with composite deck slabs form a two-storey frame; stair and canopy steel were included in the package so nothing depended on local fabrication. All parts were numbered and packed by erection sequence.钢柱配组合楼板构成两层框架,楼梯与雨棚钢构件一并纳入供货包,避免依赖当地加工。所有构件按安装顺序编号打包。
Our technician attended for four weeks: foundation bolt survey, first-bay alignment, decking sequence and facade setting-out. Local labour did the work under supervision.我方技术人员驻场四周:基础螺栓复测、首跨校正、楼板铺装顺序与立面放线。当地工人施工,我方全程指导。
The building was weather-tight in eleven weeks and occupied two months earlier than the concrete alternative allowed.建筑在十一周内完成封闭,比混凝土方案提前两个月入驻。